Specimens were fabricated in February 2012. Figure 4
provides a time line of fabrication and other project events.
Fabrication began with strand placement and stressing with
a hydraulic jack. Strands in the top flange were tensioned
first, followed by strands in the bottom flange, which were
tensioned from bottom to top and outside in.