Khun Nitithorn annual leave 19-22 Feb 2016 planned 2 month ago, new assignment below :
Group 1
Khun Jey, Khun Oil leader UAT Frozen today until complete next week Wed 24 Feb 2016, today training Frozen 6 staff coordinate Khun Anon (Frozen 8 staff on board) QSOP training before UTA activity start 9:30 or 10:00,
Khun Anon support Operation Frozen UAT
Group 2
Khun Chat support Chilled re-pallet internal and external WH, request truck transfer Chilled external WH to MC today as plan, manpower support same yesterday Chilled and FD&FT operation Khun Tob, Khun Aoe (2 Supervisor) support
Khun Angkarn support Chilled lot per lot transfer from external WH, Chilled TI x HI add 1 layer as Khun Kittinan comment yesterday (100 pallet++ put away yesterday not change TI x HI)
FT Cheese review item master current ASRS not complete request IT support as discussed yesterday as well
NOTED : Prajak join Korat meeting today