However, we may not utilize those tooling, due to the capacity of existing Tooling is enough to support our current volume. In this case , I am not sure that can we maintain the CWIP until get confirm from GSC team for utilization & capitalize asset?.
Now we have CWIP – Tooling total 130MB (including accrue which all commitment POs are confirmed active in Feb’14)
I’m sorry that our CWIP report still maintained as the Capacity expansion project, due to after revised budget last year, I got confirmed that the project was postponed to Y2014 and
I really don’t know that it was rescoped and related to efficiency not capacity expansion kha.