K. Athawout
Please provide updated shipping plan. AOS may be able to ship 88906.03 more than 1500pcs ex.fty 5/27.
Please double check with them. Also kindly provide fty weekly shipping plan enable them prioritize the items needed to ship each week.
AOS still keeps complaining that they’ve never received shipping plan from KRM.
URGENT
1) Please advise the certain soonest date RB will send all pending brown boxes and GBX to TPS and AOS.
These items were inspected since last couple weeks and last week. Fty is waiting for brown box to pack and delivery.
- Straight bowl for SWW ( inspected since last couple weeks )
- Lazy Susan triangle trays ( inspected since last couple weeks)
Kindly rush RB to finish GBX and brown box production and send to related factories ASAP.
2) Please ensure NO MISSING or late POs released from KRM for all current orders and new orders to the wood/ceramics/gift boxes suppliers.
Note : I found out that KRM just released OV PO’s to TPS qty 1000 sets on May 13 while Gibson issued this PO to KRM since Songkran which is ONE month late..
Seriously, we cannot accept this kind of repeat mistakes which causing delays shipments in the end and damages on all parties.
As discussed over the phone last Saturday, please discuss with your team and let us know solution how KRM will solve and eliminate this problem.
Missing / late issued PO’s to the suppliers is directly impact to delay the ship dates, the experience we are facing from this problem should be more than enough.
As promised,please get back with solution how KRM plan to solve this problem by Monday 5/23.