There are some costing errors I’ve noticed in JDE for G-model.
2 main things attribute to cost being so out:
- Extra parts in BOM – ECN out to get this fixed
- Total Cost (Assembly cost assigned to the Product for the main line) in Red
I want to get this corrected but unfortunately Jules Samasoni is away. I’ve been told Accounts in Thailand can help with this?
Are you able to pass on to the right person?