2 electrical engineers from 22.09. to 24.10.
o Calculation – 22.09. to 29.09.
o Specification of accessories, making of outline drawing, customer outline drawing checking and commenting, ETRA outline drawing revision, customer outline drawing checking and confirming – 30.09. to 14.10. (this point can be excluded if we can make this before engineers arrive)
o Making of documentation of tank and accessories (electric part) – 15.10. to 24.10.
· 2 mechanical engineers from 30.09. to 24.10.
o Specification of accessories, making of outline drawing, customer outline drawing checking and commenting, ETRA outline drawing revision, customer outline drawing checking and confirming – 30.09. to 14.10. (this point can be excluded if we can make this before engineers arrive)
o Making of documentation of tank and accessories (mechanical part) – 15.10. to 24.10.
If you agree with this suggestion please send me your confirmation and I will send you the invitation letters for first two engineers (please send me also names for the second two engineers).