where S is the solar energy density on tilted surface, HT (kW h/m2)
and W is the wind energy density (kW h/m2). If Eq. (5) is not realized,
stored energy in the battery will be used. The battery is considered
as full in the simulation initially and its efficiency is assumed
as 85%. The inverter’s efficiency is considered 90% here. If the total
of solar, wind, and battery energies still cannot meet the demand,
the energy shortage will be supplied by an auxiliary energy source,
whose unit cost, herein, is considered $0.5 per kW h electricity. In
this study, the location of the hybrid system is assumed in such a
place where the unit cost of the auxiliary energy is more expensive
than the electricity produced by the hybrid system. Therefore, the
cost of extra energy here is decided such that it is three times as
much of the average unit cost of the electricity produced by the hybrid
system. Otherwise, if the unit cost of the auxiliary energy was
less than that of the electricity produced by the hybrid system, the
shortage could be supplied from the auxiliary energy source all the
time without the need for such a hybrid system [5]. As seen in Eq.
(6), the auxiliary energy cost is also a part of the total hybrid system
cost. Cs, Cw, CB, Csh and CT are the unit cost of photovoltaic, wind energy
generator, battery, shortage electricity, and total hybrid energy
system, respectively. BC denotes the battery capacity. Ei is the total
amount of the electricity energy shortage because of not meeting
the demand during an hour i. Cs are $5.8/Wp (mono-crystal silicon,
rated output of 75W at 1000 W/m2), $5.5/Wp (multi-crystal silicon,
rated output of 75W at 1000 W/m2) whereas Cw is US $3/W (rated
output of 5000Wat 10 m/s), and CB is $180/kW h (200 Ah 12 V lead
acid battery) [14]. Csh is $0.5 per kW h as explained above, and n is
the simulation time period, 175,200 h. In this study, the inflation
rate and time value of money are not considered.
where S is the solar energy density on tilted surface, HT (kW h/m2)
and W is the wind energy density (kW h/m2). If Eq. (5) is not realized,
stored energy in the battery will be used. The battery is considered
as full in the simulation initially and its efficiency is assumed
as 85%. The inverter’s efficiency is considered 90% here. If the total
of solar, wind, and battery energies still cannot meet the demand,
the energy shortage will be supplied by an auxiliary energy source,
whose unit cost, herein, is considered $0.5 per kW h electricity. In
this study, the location of the hybrid system is assumed in such a
place where the unit cost of the auxiliary energy is more expensive
than the electricity produced by the hybrid system. Therefore, the
cost of extra energy here is decided such that it is three times as
much of the average unit cost of the electricity produced by the hybrid
system. Otherwise, if the unit cost of the auxiliary energy was
less than that of the electricity produced by the hybrid system, the
shortage could be supplied from the auxiliary energy source all the
time without the need for such a hybrid system [5]. As seen in Eq.
(6), the auxiliary energy cost is also a part of the total hybrid system
cost. Cs, Cw, CB, Csh and CT are the unit cost of photovoltaic, wind energy
generator, battery, shortage electricity, and total hybrid energy
system, respectively. BC denotes the battery capacity. Ei is the total
amount of the electricity energy shortage because of not meeting
the demand during an hour i. Cs are $5.8/Wp (mono-crystal silicon,
rated output of 75W at 1000 W/m2), $5.5/Wp (multi-crystal silicon,
rated output of 75W at 1000 W/m2) whereas Cw is US $3/W (rated
output of 5000Wat 10 m/s), and CB is $180/kW h (200 Ah 12 V lead
acid battery) [14]. Csh is $0.5 per kW h as explained above, and n is
the simulation time period, 175,200 h. In this study, the inflation
rate and time value of money are not considered.
การแปล กรุณารอสักครู่..
เมื่อ S คือความหนาแน่นพลังงานแสงอาทิตย์บนพื้นผิวที่เอียง , HT ( กิโลวัตต์ H / m2 )
และ W คือ พลังงานลมความหนาแน่น ( kW H / m2 ) ถ้าอีคิว ( 5 ) ไม่ตระหนัก
พลังงานเก็บไว้ในแบตเตอรี่จะถูกใช้ แบตเตอรี่ถือว่า
เต็มในการจำลองในขั้นต้นและประสิทธิภาพถือว่า
เป็น 85% ประสิทธิภาพของอินเวอร์เตอร์ถือว่า 90% ที่นี่เลย ถ้ารวม
ของพลังงานแสงอาทิตย์ , ลมพลังงานแบตเตอรี่และยังไม่สามารถตอบสนองความต้องการของการขาดแคลนพลังงาน
จะจัดหาแหล่งพลังงานเสริม
ที่มีต้นทุนต่อหน่วยในที่นี้ ถือว่าเป็น $ 0.5 ต่อกิโลวัตต์ชั่วโมงไฟฟ้า ใน
การศึกษาที่ตั้งของระบบไฮบริดจะถือว่าเช่น
ที่ต้นทุนต่อหน่วยพลังงานสำรองแพงกว่า
กว่า ไฟฟ้าที่ผลิตโดยระบบไฮบริด ดังนั้น ,
ต้นทุนพลังงานเพิ่มที่นี่ตัดสินใจนั้นมันเป็นสามเท่า
มากของหน่วยต้นทุนเฉลี่ยของไฟฟ้าที่ผลิตโดยระบบไฮบริด
ถ้าต้นทุนต่อหน่วยพลังงานสำรองคือ
น้อยกว่าของไฟฟ้าที่ผลิตโดยระบบไฮบริด
ขาดแคลนอาจจะมาจากแหล่งพลังงานสำรองทั้งหมด
เวลาโดยไม่ต้องใช้เช่นระบบไฮบริด [ 5 ]เท่าที่เห็นในอีคิว
( 6 ) , ค่าใช้จ่ายพลังงานเสริมที่เป็นส่วนหนึ่งของต้นทุนระบบ
ลูกผสม CS , CW , CB , csh และ CT เป็นหน่วยต้นทุนของเซลล์แสงอาทิตย์ , พลังงานลม
เครื่องกำเนิดไฟฟ้า แบตเตอรี่ การขาดแคลนไฟฟ้าและไฮบริดพลังงาน
รวมระบบ ตามลำดับ บีซีแสดงความจุของแบตเตอรี่ นี่เป็นจำนวนเงิน
ของพลังงานไฟฟ้าขาดแคลนเพราะไม่เจอ
ความต้องการในระหว่างชั่วโมง .CS เป็น $ 5.8/wp ( โมโนคริสตัลซิลิคอน
อันดับผลผลิตของมาร์คที่ 1000 W / m2 ) , $ 5.5/wp ( มัลติคริสตัลซิลิคอน
อันดับผลผลิตของมาร์คที่ 1000 W / m2 ) ในขณะที่ CW เป็น US $ 3 / w ( จัดอันดับ
ผลผลิตของ 5000wat 10 m / s ) และ CB เป็น 180 บาท / กิโลวัตต์ชั่วโมง ( 200 อา 12 V
แบตเตอรี่กรดตะกั่ว ) [ 14 ] csh เป็น $ 0.5 ต่อกิโลวัตต์ชั่วโมง ตามที่อธิบายข้างต้น และ N
การจำลองช่วงเวลา 175200 ชั่วโมง ในการศึกษานี้ เงินเฟ้อ
อัตราและค่าเวลาของเงินยังไม่ได้มีการพิจารณา
การแปล กรุณารอสักครู่..