I would like to confirm with your team, that our partner in Malaysia (EX-PG co) had finished the Hydrotest witness with DOSH in last week. So we expect that DOSH will issue to us the test certificate and PMT certificate in 2 weeks after the testing.
We need your support with timely payment as proposed in our proposal, in order for us to submit those documentation for Aalborg Plant. We also have to pay in soonest for all process related in DOSH certification, and we support LVT to finalize this process.