Tank 2 has been under investigation since 30 June 2014. PLIP A has been carried out twice however it has not identified any reason for the decline. Meter calibration has been done on 26/11/14 and following that we have not seen any improvement.
Due to continuous decline in tank’s performance we recommend to carry out PLIP B.