Plant X to define the required information in the unloading plan template i.e. dates of season N, bin capacity, expected hybrids, drying time (record of season N-1), production location with cobs to be sent to plant X etc.
Discussion among FP, FPP & toll plant X to enter the following data into unloading plan template: (a). planned harvesting volume by dates, hybrids, and assigned plant X ; (b). assigned bin number to contain the planned harvested batches in (a) and its required drying lead time according to hybrid-wise drying lead time average in season N-1
After entering both planned harvesting volume & assigned dryer bin, team to review and evaluate the “unloading schedule” and “dashboard” to materialise a realistic aligned plan for both FP & FPP/tolling plant, ahead of commencing season N. Make plan adjustment accordingly, in both FP & FPP/ tolling.
Required Ref. Doc. : FP Harvesting Plan (plan by grower list) AND season N-1 Drying Record