Dear P‘Supot ,
I would like to inform you about the request for approval machine list of OBOI. As I have stated in the September 9, 2013.
While this OBOI has approved the request as already.
(Image below show up to the approval of OBOI)
And make the machine release order in the “eMT system” (Electronic machine tracking system) as already.
Details are as follows :
AUTHORIZATION : อก 0906M560900004671 (Documents attached)
INVOICE NO : G-MMCT130902GY
MACHINE : USED EDGE HONING MACHINE BHT-7GY S/N No.0335 YEAR OF MANUFACTURE: 2012.06 WITH ACCESSORY
Which the cargo ship to the port of Laem Chabang tomorrow.
Next step, is the responsibility of the Shiping in contact with a customs officer, and shipped machinery to the company.
Please be informed accordingly.
Best regards,