the test shall be conducted for three trials with a duration of not less than 30 minutes per trial.during test,the rice mill shall be started and fed with the test paddy to operate continuously at the rated capacity until, the batch of test paddy prepared has passed through the mill's husker or huller.during the period , representative samples of brown rice-paddy-husk mixture , milled rice and separated components from paddy separator ,aspirator and blower shall be collected . other test data described in the next section shall also be gathered
after the test run, the discharge from the different output of the rice mill shall be collected and weighed.