Please be informed that steel structure and fabric are ready and we were ready to mobilize before end of 2015 but the footing matter has yet been sorted out.
Can you please get this done as we have another commitment to mobilize the team to Myanmar and we wanted to complete for you before.
Today Khun Surawej the structure engineer of footing designed and ours engineer have telephone conversation, which our engineer has suggest that counterweight not heavy enough and have point out about our concern and what make us doubted and today's still remain doubted about their solution of footing design. For this reason they need to looking for the appropriate solution.
We can delivery the steel structure and fabric within this weekend and can you please prepare a storage area where the products can be kept before installation work. And will wait for your confirmation for the commencement date.