Which of the following statements is false?
a. Growing grass was on the critical path for a large theme park project.
b. The critical path is the series of activities that determine the earliest time by which a project
can be completed.
c. A forward pass through a project network diagram determines the early start and early
finish dates for each activity.
d. Fast tracking is a technique for making cost and schedule trade-offs to obtain the greatest
amount of schedule compression for the least incremental cost.