Hi Nonny,
The packaging will only be ready and ship to us on the 14th July.
Shall I plan the first month shipment as below:
Est. shipment date : 18th to 24th July
5 FCLs => Orchid Brand
5 FCLs => Yacht Brand
Est. shipment date 25th to 30th July
10 FCLs => Yacht Brand
Subsequent shipment will be 5Fcls per week for the month of Aug and Sept.
Please let me know are you fine with it or you have better suggestion.