Construct ability reviews.
the PM develops a specific construct ability review program for inclusion in the quality management plan. the plan should have, as a minimum, a detailed review of the schedule associated with the work, a field visit to ascertain existing conditions and a detailed plan check of the associated design it is recommended that construct ability reviews the conducted at a minimum at the 30% and 60% completion of contract documents construct ability reviews should be conducted with regard to the expected availability of materails, and the expected availability and capabilities of local trades.