With respect to the earthwork for Conveyor's embankment for installation and commissioning of Conveyor System, the installation box cut will be provided by the Employer in accordance with the DWG. NO. C-MP-001, excluding fine grading work which will be provided by the Contractor. Once the installation box cut work has been completed, the Employer will hand over to the Contractor for further operation in accordance with an agreed time schedule, except for the embankment of the shifting conveyor C1 (DWG. NO. C-MP-001) which the Employer shall hand over to the Contractor six months before the Commencement Date