Dear Khun Opas,
The balance quantity Fig.8 24C AR : 80km will delivery on 20-21/July.
Normally from the P/O until to the delivery date : 40-45 days. We have only 1 day (Friday) in a week that the vessel on board from China port. If the schedule not match with Friday, we have to wait to on board on the next Friday.
Now we do the plan to stock the cable for your company to avoid the late shipment, we will send you to approve the cable marking next week. The quantity that we will do to keep the stock are as below :
Fig.8 24C AR : 100km
Fig.8 96C : 48km
Fig.8 96C AR : 48km
Please advise if you have any recommend for the quantity of stock.