The subsoil immediately below the seabed surface consists of a
thick, weak Holocene clay layer, which should be improved so
as to minimize the residual or uneven settlement after the air-
port open its operation and to ensure the stability during the
seawall construction and reclamation. The ground improvement
work was carried out throughout the entire seawall and reclama-
tion area.