I have earlier requested all of you that this is a very important Report and should be Analyzed and checked before sending. It is a good practice that all concerned Engineers & HOD analyze this report in morning. This will give you a good idea about the efficiency of your area and you can focus on the problems found.
1) Compressor No. 2 The Compressor No. 2 is running with 5731 Units on AI .
This is including N2 . Pls. mention in this report also . Pls. also mention the Load / Unload hrs. for this.
2) Compressor No. 10 is not running , but it is showing Running Hrs.23 and Loading Hrs. 24.
Pls. also report on below items -
3) Pls. check the Load on Chiller No. 2 & 5 . Pls. discuss.
4) Please inform me the Running parameters of DTY Chiller. Pls. show me the Log Book. What is the Hot Water Temp. now?
5) Are you running the Chilled water Inline booster pump now ? Pls. run and see if the Load on DTY Chiller can increase .