on June 9, we have test packing salt as taget stock 9 tons during 8.00 am.to 4.55 pm.
For test salt Packing we have some problems in process as below
1.we don't have enough employees to prepare the fold packing box per day.
2.we don't have enough time to stop the machine for clean up.
3.Before start the Process we losed the time to clean up the machine about 1.30 hours, however we have salt to finished goods on May 10, amout 7 tons.