Again.. Just been informed during today site meeting as to date TRUE has not continued the installation at L7,8,9 as yet !!
With TRUE delays , Pls be informed that all necessary modification works requested by TRUE to the project completed works e.g. wall,floor,ceiling etc. in order to install TRUE remaining works must be responsible by TRUE 100%