Our proposal is based on understanding of how to manage Asean Market Development Project with our experience and manpower during service period. proposed schedule is calculated with many assumed factors in idle situation, the schedule may be adjusted upon development of project. The Preliminary milestone schedules of the project are as follows.;
Our sevice period shall be 8 months for the 1st service package May 2014 to December 2014 and 60 months for the second service package from January 2015 to December 2019. In case of delaying of project without default of consultant, project service period shall be adjusted accordingly.