We are now asked to answer the following questions:
1) What is the total completion time of the project?
2) What are the scheduled start and completion time for each activity?
3) Which activities are critical and must be completed exactly as scheduled in order to keep the project on schedule?
4) How long can the non-critical activities to be delayed before they cause a delay in the completion time for the project?