Dear all L/D BD and Prayong san
From now production delay from plan estimate -1,000 tires.
So PP need to revise shutdown plan for shutdown schedule will be delay from plan on April 10, 2015 shift .
From mold of last curing open 5:30 => 8:30 for recovery production delay.
So I got request from 85 for request MM support for takeout tire from curing c/v for keep in rack.
Because inspection process already stop.
So I request support OT from MM BD in shift 3 of April 10, 2015. For this matter.
To make OT until 12:00 then go home for support production carry tire from c/v to rack.
510B3
Please summary name list for volunteer of this OT work for me.
I need to know. How many person can be working for us.
And send to me within Monday April 6, 2015. 10:00
For send data to 85 and 600
FYI. Thank you.