Within a jointed reinforced concrete pavement, the quantity of reinforcement
directly determines the joint spacing. If the slab is unreinforced and less than
230mm thick, contraction joints should occur every 5m. If the unreinforced slab
is above 230mm, these spacings reduce to 4m