TRC Review Priority Points – Feb’15
1. Safety :---------------- Wallop/Chaveang/ Ashish
a. Major Incidents in last 1 year. Action Plan and Way Ahead
b. Fire Incidents
c. Progress of Unit Safety Committees
2. Status of Cost Saving Initiatives ---------Mahendra
3. Progress on TRC Sustainability Program – Value Added Fibre - Sushil
a. Micro Denier
b. Coarse Denier
c. Non Woven
4. Dyed Modal on Line #2: ------------- Sushil
a. Feasibility to be established.
b. To share detailed action plan to arrive at the decision considering expected quality of Dyed Modal Produced and effect on quality of other lines (if any)
5. Steam Power Stability: ------------Pradeep Sharma
a. New Captive Power Plant
i. Alignment with community and Environment clearance - Action Plan to achieve this
ii. Configuration Finalization
b. 30 TPH Boiler : Unit had taken stretch target of commissioning by Feb’15. But it seems commissioning will only happen in March’15 ------------Manoj Mittal
c. Existing 20TPH boiler in Bad shape. Need refractory repair and tube replacement. To be taken up after commissioning of 30 TPH boiler --------- Ashish
6. CS2/H2S Reduction by CAP: ----------RGA
a. Progress against Target and expect timelines
b. Concerns if Any
7. Quality ---------- Sushil/ Neeraj/ Navneet
a. FPY: Major issues resulting in variation in Ball Fall and % Cellulose. Action Plan to resolve the same.
b. Gradation: Unit consistently achieving <2% offgrade. However, in Line #6 there is complaints of inconsistency.
8. Chimney Status: ------------ Sandeep Sharama
a. Observations from the first inspection and Action Plan
b. Knowledge sharing with other units
9. Commercial Issues - Pramod
a. BOD/COD Levy: Status of approval and promulgation of Law. Our Liaisoning Status
b. Overtime Payment on COLA
c. Status of Reduction of Inventory and Working Capital improvement
d. Any other Important Point
e. ITS/ILT – Payments on Hold
10. Detailed presentation --- Technical Cell with the support of all DH/ RGA/Sushil/ Ashish/Pramod
การแปล กรุณารอสักครู่..