Regarding as mail below
1. My project guy have to sending UL drawing to your M&E guy 2 week ago as option Kitchen –lay out revision 19 as mail below ,Am not sure they have to got it or not ? if not pls. use this link below
Morimoto UL-Drawing
UL-01 R05
UL-02 R05
UL-03 R06 new update
UL-04 R06 new update
UL-05 R07 new update
UL-06 R07 new update (3 sheet cancel Gas system )
UL-07 R05
Link http://nas.alliedmetals.com:80/share.cgi?ssid=0yfty6D
2. Next you have to Approved Kitchen –lay out revision 19 and perspective drawing by each item of the S/S equipment BY hard copy of date 5/12/15 ,
This revision 19 drawing have some additional, cancel ,replace equipment with Import and S/S Item SO we must have to revise the Quoted too ,Now on the process with our admin , and hope fully can sending to you approval as well with early first week of January
3. Than A few week you needed revised some item of the kitchen lay out to revision 20 ,Am not sure you still needed to change or remaining as Revision 19 ,If you have any conclusion feel free to let’s me know shortly ,because have the effect with production line and equipment
4. About the cold room :Now the panel and compressor system ( Air cooled ) already in warehouse and well ready to installation if the site finish ,
5. Hood Halton 3 item : as you reply mail to me with approved and give to Project 7 –M&E guy sign shop drawing ,I still need the drawing with signature than I well sending to Halton for fabricates and we can’t any adjust of FCM more than attached file our project guy sending to you ,this is concerning lead time
6. Import item status we can’t to change because already in ware house ,and for the Import additional item well let’s you know the schedule again after you part have to sign confirmed of BOQ
7. The fabrication item status we transfer shop drawing approved from you to factory 2 week ago ( Only first ordered )than well have plan to start delivery on end of January and additional item also well let’s you know the schedule again after you part have to sign confirmed the BOQ too
8. The latest our Schedule installation team as attached file