Please ask our subcontractor (K inter , Khun Somsak) to propose the quotation for Electrical Work/ Instrument Work for Zone 1 and Storage area (Warehouse) as per Scope and BOQ attached:
Document to send out:
1) General info: Show Site location, General Requirement, transformer location, existing and new building location
2) Scope of Work: Define scope of work
3) Motor and Instrument List: For reference
4) BOQ: Please follow item/quantity in BOQ, any items need to be added to complete the scope shall be insert in the table with red mark
5) Process Layout: For reference
6) Building Layout and Control Room: Show Building Layout Zone 1 and Warehouse, enlarge electrical / control room with panel size
7) Vendor Brand
8) NOTE: Process motor list / instrument list will be sent later for reference, currently please follow BOQ form
Require Document return
1) Quotation and BOQ back in next week 4 May 15
2) Indicate manpower / Schedule to work