I get have info form PC about that Escutcheon to have problem about clear panel in process Ass’y. And unable support part follow by CAT req.
(Escutcheon under model of NCG2 under supplier Metco.)
Therefore maybe our PC will be switching another model relate NCG2 to anther.
Now situation of Nissha have problem about process pull in shipment . Since PO shortage L/T.
This’s cause. I have concern the quantity of part not enough to support production line.
Nissha have separate quantity of part per shipment. Therefore I have very concern about part shortage and line down.
Pls. you note and discussion with PC as well.