From our inspection of the existing structure, we have found the framing plan as specified in our tender drawing except for the ground floor slab which we could not get underneath it.
However, we believe that once the demolition of this ground floor slab is carried out, then, we can be able to confirm the framing plan and we can still provide the structural modification for this part.
Also, as it is confirmed by dumb waiter supplier that the height of overrun and mechanical can fit with the height from L1 to the underside of L2, we will revise our tender drawing by deleting any structural modification on L2 and this can be submitted to you on Mon.
From our inspection of the existing structure, we have found the framing plan as specified in our tender drawing except for the ground floor slab which we could not get underneath it.However, we believe that once the demolition of this ground floor slab is carried out, then, we can be able to confirm the framing plan and we can still provide the structural modification for this part.Also, as it is confirmed by dumb waiter supplier that the height of overrun and mechanical can fit with the height from L1 to the underside of L2, we will revise our tender drawing by deleting any structural modification on L2 and this can be submitted to you on Mon.
การแปล กรุณารอสักครู่..