(g) M and N succeed F, but cannot start until both E and H are completed.
(h) 0 succeeds M and I.
(i) P succeeds 1, L, and o.
(j) K, N, and P are the terminal activities of the project.
3. The footings of a building can be completed in four consecutive sections. The activities for each section include (1) digging, (2) placing steel, and (3) pouring concrete. The digging of one section cannot start until that of the preceding section has been completed. The same restriction applies to pouring concrete. Develop the project network.