Please note that all information about LBS, RCS and PAC concerning work progress, main defects and others are in the PDM and they are summarized in the exelfile: 151022 SVK PDSR work progress status & plan already sent to you with the last 151022 Daily report PDSR in the previous e-mail message from me.
Anyway, if you have any questions, don’t hesitate to send your question by e-mail message.
Note that generally the work plan, when there is a work plan, may be changed every day every time without advising from Enova or subcontractors, so, it is important that you survey the work with formal manner with Enova and subcontractors but also (in parallel) informal manner with discretion too because sometimes Enova is short-circuited by EDL and Subcontractors have several teams that can work simultaneously in different areas;
Have a nice and pleasant work.