Upon receipt of the signed/approved CN, the MCC shall advise the Project Manager(s) of the outcome so that work may proceed accordingly. Any instruction to a Contractor is to be made in writing through the Company Contracts Administration Department following the Contract Variation Order Request (VOR) and Variation Order (VO) procedures.