Dear Khun Chalee,
Referring to Vitamin Water project, we would like to update the situation for the shipment of the machine which will arrive your plant for your reference.
This is the estimate schedule for your information and prepare the location for unloading process and keep the packages at your plant as per the attachment.
1. Conveyor
3 containers ( 8 packages)
ETA Ya-in Thai plant : 22-23/12/15
2. Filling Line
9 containers ( 20 pallets / 4 case )
ETA Ya-in Thai plant : 26-28/12/15
3. Process & Tank
3 containers ( 2 Tanks & 1 box )
ETA Ya-inThai Plant : 7-8/01/2016
Our team will prepare on the unloading process at your plant. The exactly schedule, we will keep you inform once we got the update information.
Should you need any information, please do not hesitate to contact us.