) We are past due on 600 Inputs - due date was February 8. We are waiting for new PO from Magna on the Input and Output Shafts since we gave them a large increase. RS will not be shipping until we receive the PO.
2) There is 300 parts in transit.
3) We have 300 at RS now to be machined soon.
4) Yes. We need 1,200 more parts to be shipped to cover orders.
Regards,