Dear Kajohnkiat,
here my comment on drawing:
1 - transformer yard:
This drawing doesn’t contain measures, description and separation into single drawing sheets. If we pay for subcontractor (EE) to make drawings for us, we can should get complete drawings, no sketches. Please organize complete drawing us we get usually.
2 – Diesel generator:
The file is empty, no drawing. Please check and resend.
3 – Feed water pump foundation
We will release piling plan on tomorrow and send you the details for the foundation. EE need to update do the detail drawing for foundation accordingly.
4 – Cooling water pump foundation
We will release piling plan on tomorrow. Details for the foundation are not available jet – we will send after pump order.
5 – cooling water pipe rack
We will release piling plan on tomorrow. There is a modification in design that was not concluded from us (2 columns at TG building missing). We will discuss later.
For all foundations:
Please provide pile calculation printout.