We would like to inform you about deliver Prop Shaft 5JX2904960 1 pc(POT-1071) .
Schedule as below
Load on 15 Jan 2016
ETD on 16 Jan 2016.
We have a problem about deliver incorrect between Yoke; Spline (156-084070) order with Prop Shaft 5JX2904690 at port BKK which Yoke; Spline is fix order.
We must be clear Prop Shaft leave the port BKK first.
Prop Shaft 5JX2904690 may delay from ETD on 16 Jan 2016.
If we have more information we will let you know immediately.