Dates. The closing date was extended five times. On December 19, 2007 by 6 months to June 30, 2008, on June 24, 2008 by 18 months to December 31, 2009, on September 17, 2009 by 6 months to June 30, 2010 in order to allow the project team to process the Additional Financing, on April 6, 2010, when the Additional Financing was approved, by 18 months to December 21, 2011, and on December 29, 2010 by 6 months to June 30, 2012. The project closed 4 1/2 years after the original closing date.