3.8.1 The Contractor shall be responsible for the safeguarding, care and custody of the Plant and all of its equipment located or stored at the Site excluding any equipment or materials owned or provided by the Owner located on the Site during the execution of the Works (to the extent such Owner’s Equipment and materials are not used for the Contractor’s performance of its obligations under this Contract) until the date of issue of the Provisional Acceptance Certificate.
3.8.2 The Contractor shall promptly replace, at its own cost, any Component Parts damaged or stolen prior to the Provisional Acceptance Certificate being issued under this Contract.