The consultant determined the approximate base load of the equipment in the
proposed data center and suggested a raised floor design. The floor area was
divided into functional areas such as NOC area, equipment staging area, network
room, and data center area, which would have rack rows containing
servers, storage, and other devices. Some floor area near the entrance was
marked for large floor-standing servers and storage subsystems (which are not
designed for racks).