Procedure of work
Refer to your RFA's approval change plan discusses issues that occur by claiming that we have sent a Drawing after the concrete was completed, which we checked that you did not send a Shop Drawing to submit for approval work in advance.
So in order to prevent such an event happens. We emphasize again, as has been in 1st meeting that you must send a Shop Drawing for approval to work at least 3 days in advance, Otherwise we will not allow you to perform any action in any case.