Hi Jon,
1. In parallel to below email and board received from Ms Yasuko, we have completed the 100% inspection of the 3 cartons of current production, as discussed last week in PRB with JAL.
a. The findings are in the attached file “160630 PRB 100%…”.
b. 2 of the findings are differences with the master samples of PRB, however they might not be considered as defective (the number 1, Dent, has no impact on product functionality and safety, and the number 5, hard point on the rim, is not possible to avoid with the new SRK machine process).
c. Before sending the report (and samples to JAL), we would like to send them to you (or…) for review; please comment (where to send).
2. Regarding the below comments from the report of meeting, see below.
Thank you and best regards,