Delays that have occurred at the beginning of the project are now having a delaying effect on the production of the remaining façade panels for the tower. PISA’s factory, in Chonburi that produces the Central Embassy panels cannot remain idle waiting for projects. Once a project is given a period of time for production there cannot be any substantial delays to the commencement of the production otherwise other projects will take their place.