Workflow total float is also the maximum delay of
all critical activities. To maximize the time interval of
each critical activity, the total float is segmented
equally and assigned to all critical activities (except for
dummy activities). as denotes the float of a critical
activity, the maximum delay of the activity. | p(n) |
denotes the number of critical activities. Then