We need to cancel for the bulk emulsion for both site on etd : 25/11/2559 cross border : 26/11/2559 because of BHX site ,We waiting for the tank return and Phukham site ,Now TKPV team onsite advise me cancel due to the silo onsite are cannot load bulk emulsion. there is overload while the crane on brake for fix. If there is anything please contact to Mr.Nattavut (Head of Phukham team) for any question about schedule for ANPP and bulk emulsion as we need to change.