Dear all,
The Mixing1 fabrication will have finished in next week, WK42, including passivation and cleaning by Ecolab on Mon17 and other activities as below plan,
Attached are hygiene & maintenance and passivative cleaning guideline shared by K.Auh –QA, for your reference on maintenance and new equipment cleaning method,
K.Auh,
I got confirmation about passivation and cleaning by Ecolab will be held on Mon13, you are invited to join discussion nakrab.
Regards,
Montree
Dear all,The Mixing1 fabrication will have finished in next week, WK42, including passivation and cleaning by Ecolab on Mon17 and other activities as below plan,Attached are hygiene & maintenance and passivative cleaning guideline shared by K.Auh –QA, for your reference on maintenance and new equipment cleaning method,K.Auh,I got confirmation about passivation and cleaning by Ecolab will be held on Mon13, you are invited to join discussion nakrab.Regards,Montree