Dear Much & Chaz,
This first Type “E” RC unit in Funan has been started up online since 12 Sep with not yet accepted for an official handover (being under SR for a 3-month transition period to allow Exterran O&M team to work on during punch list items execution).
And since 9 Oct until at present, there have been several problems encountered with repetitive high LPO as depicted below and on above attached. Note that this unit was gaining production at about 5 MMscfd.
Luckily that this unit has not yet been registered for LPO tracking by Base Business due to the requested 3-month transition period (Sep – Nov) which is already overdue.
Now that, I need both of you work out with the field to collaboratively develop a more stringent solid plan for this unit ASAP.
So as to proactively develop a plan ready for the upcoming commissioning online (targeted for Jan 15?) of the GL-RC unit on SGWC, which is another first Type “D” (Model GLD-18) in Funan too.
The field focal point is Funan Field Engineer (Supapong & Natthaporn).
Thank you in advance and I look forward to work closely with both of you again in Platong from next month onward,
Sorayuth Y.