To enable the activity to be costed in the corresponding
measurement period, it is convenient to split this up into two-weekly periods of
$4,700. Hence in Figure 31.5, foundation excavation for building A is shown as 47 in period 1
47 + 47 = 94 in period 2
47 in period 3