Reference is made to your letter Ref no. CK/PLC4/2280/59 dated 08 August 2016. To ensure the continued project hazard of the MRT Purple Line after commencement of revenue service, by follow the GS Annex 2 – System Assurance Requirements (item 4.3 Hazard Analyses and Hazard Log), the information and tools of the System Hazard Log shall be handed over to Operation. Before this is happened, we would like you to prepare